Case Study
How We Reduced Setup Time on a 5-Axis Cell
1 July 2026 • Lee Sanders
A Midlands subcontractor running a 5-axis cell was struggling with recurring setups. Each new job seemed to start from scratch: fresh fixtures, fresh tooling, fresh proving-out.
We focused on three things:
- Fixture standardisation. A small library of reusable fixture bases cut the number of bespoke setups by 60%.
- Programming discipline. Templates and consistent tool naming meant programs were readable and maintainable by more than one person.
- Setup sheet discipline. Clear, photo-led setup sheets reduced the reliance on memory.
The result: recurring setup time dropped by more than half, and the shop could quote shorter lead times with confidence.